PLAY
Full design & build process for Play office in Warsaw
PLAY
Full design & build process for Play office in Warsaw
Area: 10 000 m2
Start: 26.04.2013
Delivery: 30.09.2013
Services:
- Preparation of Space Plans of the arranged space
- Technical advice on the lease agreement
- Preparation of technical attachments to the lease agreement
- Coordination of design works
- Architectural design
- Design of electrical installations
- Design of sanitary installations
- Installation of DSO and SSP
- Execution of construction works
- Execution of electrical installations
- Execution of sanitary installations
- Supervision over the arrangement works in progress
- Handing the area over for use
- Post-completion documentation
Location: Warsaw